No. of :

No. of Shares:

Currently viewed by: Marcus Rosit

DPWH commences tunnel excavation work for Davao City Bypass Project

MANILA -- The Department of Public Works and Highways (DPWH) is ramping up efforts to improve the transport logistics and mitigate vehicular traffic congestion in Davao City with the construction of a 2.3 kilometer two (2)-tube mountain tunnel. 

A symbolic blast on Friday, November 19, 2021 officially started work on the road tunnel which is part of the 10.7 kilometers Contract Package I-1 of the Davao City Bypass Construction Project (DCBCP) implemented by DPWH Unified Project Management Office (UPMO) Operations. 

The actual commencement of tunnel excavation works was witnessed by DPWH Acting Secretary Roger G. Mercado, Japanese Ambassador to the Philippines Kazuhiko Koshikawa, DPWH Undersecretary for UPMO Operations and Chief Implementer of Flagship Projects under Build, Build, Build (BBB) Program Emil K. Sadain, and Japan International Cooperation Agency (JICA) Chief Representative Eigo Azukizawa. 

The short program, carried out under strict compliance to health policies, was also attended by Undersecretary Eugenio R. Pipo Jr. and Assistant Secretary Ador G. Canlas of DPWH Regional Operations in Mindanao, Embassy of Japan in the Philippines Second Secretary Matsubara Tomohiro, DPWH Region 11 Director Rey Peter Gille, Project Director Benjamin A. Bautista of UPMO Roads Management Cluster 1, former Project Director Virgilio C. Castillo, Mr. Fidel Arcenas of the Office of DPWH Secretary, and other Japan Embassy and JICA officials. 

According to Undersecretary Sadain, the tunnel project which will soon be the first-ever long-distance mountain tunnel in the Philippines was designed by Japanese experts to have better seismic resiliency. 

To support the underground development, equipment that includes horizontal boring machine for geotechnical investigation, twin header tunnel excavator and drill jumbo are deployed to work at the north and south portal. Additional equipment on the ground also includes erecter with shotcrete machine, tunnel ventilation and dust collector, side dump payloader, and articulated dump truck. 

The civil work contract for the construction of the tunnel was awarded to Shimizu – Ulticon - Takenaka  joint venture with Nippon Koei – Katahira - Nippon Engineering - Philkoei as engineering consultant  under the overall project construction supervision of UPMO-RMC 1 Project Manager Joselito B. Reyes and Engr. Earl Nicholas F. Rada. 

This contract package costing P13.230 Billion has an estimated completion date of January 2024.

While construction of the tunnel is the centerpiece of this project contract package, there are other significant portions of the work as well.  The contract includes the construction of a  7.9 km 4-lane road, 3 pairs of Bridges with a total length of 500 meters, 2 underpasses, 2 overpasses, 12 box culverts (waterways), and 4 at-grade Intersection. 


The 45.5 kilometer bypass road that will begin in Barangay Sirawan, Toril, Davao City and will end at Barangay J.P. Laurel, Panabo City will cut the usual travel time of 1 hour and 44 minutes via Maharlika Highway to just 49 minutes. 

Together with rapid population growth and economic development in recent years, DCBCP will provide job creation during construction, and economic benefits through reduced travel time savings across the city, said Undersecretary Sadain.

The entire DCBCP is divided into six (6) contract packages with packages I-1, I-2 and I-3 being financed by JICA Loan Agreement Nos. PH-P261 and PH-P273 while packages II-1, II-2 and II-3 are funded by the Government of the Philippines. (DPWH)

About the Author

Kate Shiene Austria

Information Officer III

Information Officer III under the Creative and Production Services Division of the Philippine Information Agency. 

Feedback / Comment

Get in touch