No. of :

No. of Shares:

Currently viewed by: Marcus Rosit

Construction of Bambang Bypass Road Project reaches 60%

The Bambang Bypass Road Project in Bambang, Nueva Vizcaya is now 60.47 percent accomplished. Once completed, the project will reduce traffic and boost the economic potentials of the town. Photo from DPWH 2 FB Page

BAYOMBONG, Nueva Vizcaya (PIA) - - The Bambang Bypass Road Project in Bambang town is now 60.47 % accomplished.

DPWH Regional Director Nomer Abel Canlas said the P703.65 million project  involves the construction of a 4-lane concrete road measuring a 13.4-meter carriageway width, 300-millimeter thickness with a total length of 5.423-kilometer including two concrete bridges and Road Right of Way (RROW) acquisition.

“Once completed, the travel time from Cagayan and Isabela to Manila will be reduced up to 20 minutes and it will benefit almost 25,000 travellers per day upon completion of the project,” he said.

Canlas said the project will provide safe and efficient highway system that will accelerate the delivery of local farm produce as well as the enhancement of tourism and economy in Nueva Vizcaya.

“It is seen to build new communities and provide livelihood opportunities for business development, tourism, employment, and socio-economic activities,” he said.

The Bypass Road Project traverses barangays  Almaguer North,  Buag, Calaocan, Homestead, and  Macate in Bambang town. (MDCT/BME/PIA NVizcaya) Photos from DPWH2 FB Page

About the Author

Benjamin Moses Ebreo

Information Officer III

Region 2

Feedback / Comment

Get in touch