NIA-6, Drilon ginpasalamatan ang suporta ni PBBM sa JRMP II

SYUDAD SANG ILOILO (PIA6) – Gin-aprubahan sang damlag lang sang National Economic Development Authority (NEDA) ang kapin P8.48 billion nga loan restructuring para sa pagtapos sang Jalaur River Multipurpose Project Stage II (JRMP II) sa Calinog, Iloilo.

Bangud sini, ginkilala kag ginpasalamatan sang National Irrigation Administration (NIA)-6 kag ni anay senador Franklin Drilon ang suporta nga ginhatag ni Pangulong Ferdinand Marcos Jr., nga amu man ang nagapungko bilang chairman sang NEDA Board, para sa padayon nga pagpatapos sang proyekto.

“Let me give our acknowledgement and appreciation for the support of the Marcos administration on the building and completion of this dam. The President, as chairman of the NEDA approved the continued construction and completion of this project with availability of the funds,” pahayag ni Drilon sa iya pagbisita sa JRMP II site sang Oktubre 18, 2023.

Suno kay Drilon, nga isa sa mga nagduso sa pagpatuman sang proyekto sang ara pa siya sa Senado, nga kung mangin operational na ang JRMP II sa 2025, makabulig ini sa pagsabat sang food security kag pagsolbar sang mataas nga inflation rate, nga amu ang pila man sa ginatutukan sang administrasyong Marcos.

Nagapati si Drilon nga kung mangin operational ang dam, magasaka ang ani nga palay sang mga mangunguma sa probinsya sa masobra 300,000 metric tons kada tuig bangud man sang tayuyon nga supply sang tubig sa mga irigasyon.

“Iloilo used to be the rice granary of the country. Today, we no longer enjoy the status. But once the dams are completed and fully functional, from the present 100,040 metric tons of palay, it would increase to 300,000 metric tons per year. Therefore, not only will we be sufficient, but we will also be an exporting province,” siling ni Drilon.

Sa pihak nga bahin, ginpahayag ni NIA-6 acting manager kag JRMP II project manager Engr. Jonel B. Borres nga luyag nila maging dinapit kag mapangunahan ni Marcos ang inagurasyon sang JRMP II kon matapos ini sa tuig 2024.

Basi naman sa datos sang NIA-6 sang Setyembre 2023, yara na sa 69.23 percent ang physical accomplishment sang proyekto, kung sa diin duwa sa tatlo sini ka mga dam ang makabig na nga “substantially completed.”

“Currently, the Jalaur High Dam, the reservoir dam of the project which is expected to store a volume of water estimated at 250.70 million cubic meters, is already 106-meter high out of its structural height of 109 meters. Located in Barangays Agcalaga and Alibunan in 

the Municipality of Calinog, the High Dam will ensure year-round irrigation water supply to 31, 840 hectares of farmlands in the Province of Iloilo,” pahayag sang NIA-6.

Samtang ang Jalaur AfterBay Dam, nga magahatag sang tubig pang irigasyon sa mga kaumahan sa Zone 1 sang proyekto kag maga-regulate sang tubig halin sa impounding dam pakadto sa High Line Canal, ang makabig na nga “substantially completed” sa kataasun nga 38.5 meters.

Ginalauman nga ang JRMP II makahatag sang irigasyon sa 31,840 hectares nga talamnan sa Iloilo; maka-generate sang 6.6 megawatts sang hydroelectric power, 86 million liters nga bulk water sa probinsya kag syudad sang Iloilo kada adlaw; kag maka-bulig hagan-hagan sang pagbaha sa Calinog kag kalakip pa nga mga banwa.

Gintumod man sang NIA-6 nga ang JRMP II ang makabulig sa pagpalapad sang production areas sang tubo sa Iloilo kag pagpataas sang produksyon sang palay tubtob 71.54 percent ukon 338,874 metric tons kada tuig. (AAL/JNH/PIA6 Iloilo)