No. of :

No. of Shares:

Currently viewed by: Marcus Rosit

TRB: 3rd Candaba Viaduct project on track for completion by November 2024

MALOLOS CITY (PIA) -- The Toll Regulatory Board (TRB) reaffirmed its commitment to the public that the 3rd Candaba Viaduct will be completed by November 2024.

Spanning five kilometers, the infrastructure is situated between two existing bridges connecting the towns of Pulilan in Bulacan and Apalit in Pampanga.

TRB Executive Director Alvin Carullo cited the report of North Luzon Expressway (NLEX) Corporation that the project is now 50 percent complete.

“The installation of the first girders in the first two spans in the Pulilan section signifies the project’s halfway mark and the start of the pivotal transition from groundwork-heavy construction to road-level work,” he said.

A total of 1,028 girders are scheduled to be installed in the whole stretch of the viaduct.

NLEX Corporation begins the installation of the first girders in the first two spans in the Pulilan section of the 3rd Candaba Viaduct. This signifies the project’s halfway mark and the start of the pivotal transition from groundwork-heavy construction to road-level work. The infrastructure is on track for completion by November 2024. (Shane F. Velasco/PIA 3)

The construction of posts and the drilling of foundations are likewise in full swing in the Apalit portion.

Meanwhile, NLEX Corporation President and General Manager Luigi Bautista recognized the vital role of construction partners from Australia and the Philippines in speeding up civil works while ensuring the quality and integrity of the new structure as well as the safety of construction workers.

The P8 billion project is being built by Australian firm Leighton Construction Asia Limited with its local partner subcontractor Megawide Corporation.

Once completed, the Candaba Viaduct will be widened to three lanes with inner and outer shoulders in each direction, thereby enhancing safety and mobility for motorists.

The inner lane in both directions will be used for trucks and buses while the old and original structure will be the assigned lanes for light vehicles. (CLJD/SFV-PIA 3)

The construction of posts and the drilling of foundations in the Apalit portion of the 3rd Candaba Viaduct is now in full swing. This is part of the 50 percent progress rate in the construction of the infrastructure which is on track for completion by November 2024. (Shane F. Velasco/PIA 3)

About the Author

Shane Velasco

Writer

Region 3

Feedback / Comment

Get in touch