No. of :

No. of Shares:

Currently viewed by: Marcus Rosit

DPWH works on foundation of Panguil Bay Bridge

MANILA --  Public Works and Highways Secretary Mark A. Villar announced that the on-going works for the Panguil Bay Bridge Project stays on track within the target completion of December 2023.  

Secretary Villar said that progress of works for the Northern Mindanao’s mega inter-island connection is now at 22 percent as major equipment intensifies preparation of the bridge foundation.  

In an inspection report to Secretary Villar, Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain said that 15 bored piles out of 54 for Panguil Bay Bridge sub-structure were completed to date at a depth ranging 30 to 50 meters.  

Undersecretary Sadain together with Project Director Sharif Madsmo Hasim of UPMO Roads Management Cluster 2 conducted work performance assessment on Thursday, August 5, 2021 of the off-shore construction activities by Korean joint venture contractor Namkwang-Kukdong-Gumwang.  

Based on the extensive detailed engineering design, the 3.169 kilometer Panguil Bay Bridge will require 54 bored piles intended for the 32 piers, two (2) for abutments at Tangub City, Misamis Occidental and Tubod, Lanao Del Norte side, and two (2) for pylon of the main bridge.  

Bored piles 3 meter diameter are completed using reverse circulation drilling machines on barges to prepare the bore holes followed by the launching of 23 millimeter thick permanent steel casing using revolving crane barges and vibro pile hammers, and until final pouring with two (2) land and sea-based batching plants each capable of supplying 120 cubic meter of ready-mixed concrete per hour.  

With an average of six (6) to seven (7) holes prepared per month, 74 percent or 40 of the 54 bored holes is targetted for completion towards end of December 2021 with the remaining 26 percent or 14 bored holes to be finished by February 2022.  

In order to ensure quality of works, the completed bored piles are subjected to checking using cross hole sonic logging test after 7 to 14 days of concrete placement  in order to assess the integrity of concrete in  the cast-in-site pile and will also undergo pile loading test to determine the safety factor, Undersecretary Sadain reported.  

Considered as the biggest and boldest infrastructure project in Northern Mindanao, the P7.375 Billion project to connect Tangub City and Tubod across Panguil Bay in just seven (7) minutes is funded by a loan agreement between Government of the Philippines (GOP) and Korean Export-Import Bank (Korea Eximbank).  (DPWH)

About the Author

Kate Shiene Austria

Information Officer III

Information Officer III under the Creative and Production Services Division of the Philippine Information Agency. 

Feedback / Comment

Get in touch