The tunnel construction works for the Davao City Bypass Construction Project started at north portal on November 19, 2021 for southbound direction, and on December 10, 2021 for the northbound direction.
Meanwhile, excavation activities from opposite end at south portal commenced on May 12, 2022 for northbound direction and on June 9, 2022 for southbound direction.
After the activities at north portal was temporarily halted by water seepage on the tunnel roof, the use of Japanese waterproofing technology and materials has helped the DPWH and its contractor addressed this problem.
Other than the tunnel, contract package 1-1 involves the construction of four-lane road with a length of 7.9 kilometers; three (3) pairs of bridges with a total length of 500 meters including the Davao River Bridge; two (2) underpasses and two (2) overpasses; 12 waterways culverts; and four (4) at-grade intersection.
This on-going contract package 1-1 costing ₱13.23 Billion is financed by Special Terms for Economic Partnership (STEP) Loan between Philippines and Japan International Cooperation Agency under loan agreement numbers PH-P261 and PH-P273.
The Davao City ByPass Road Construction Project is being implemented by DPWH Unified Project Management Office - Roads Management Cluster 1 (Bilateral) headed by Project Director Benjamin A. Bautista and under the on-site supervision and monitoring by Project Manager Joselito B. Reyes and Project Engr. Juan M. Diña Jr. with Nippon Koei – Katahira - Nippon Engineering - Philkoei as engineering consultants.
Once completed, the entire bypass road will slash travel time between Toril, Davao City and the northern Panabo City, Davao Del Norte to under 49 minutes from the usual more or less two (2) hours via Maharlika Highway. (DPWH)